Download Scenario 1, 2 & 3 from Material Tab.
Examination Procedure
Examination Format
0 of 32 questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 32
Time has elapsed
0 of 0 point(s), (0)
0 of 0, (0)
Essay(s) Pending: 0 (Possible Point(s): 0)
Refer Scenario 1 – Which of the following can be categorized as a benefit of the project?
Refer Scenario 1 – Which of the following can be stated as a ‘Reason’ to undertake the project?
Refer Scenario 1 – Owing to the strategic importance of the project, the CEO of ABC Company decided to become a Project Sponsor. The project sponsor is responsible for the project business case …
Refer Scenario 1 – The business case had projected a saving of 20 million USD over 10 years in operating cost as a result of the implementation of the project. During the project execution, the project manager realized that a saving of only 10 million USD was possible. What should the project manager do?
Additional Information – “During feasibility study ABC Company management studied a list of internal projects envisioned. The management shortlisted projects to start with. The management analyzed the organization’s strategic objectives, investment required for the projects and the business need.” What additional aspect should be considered while making this decision?
Refer Scenario 1 – The Project is divided into 4 stages. A stage gate meeting is planned at the end of every stage. What is the primary objective of Stage gate review?
Refer Scenario 1 – The project life cycle of the project is divided into four stages based on the recommendations. The first stage is Initiation stage. Which of the following statements is NOT true regarding this stage?
Refer Scenario 1 – Owing to the strategic importance of the project, the CEO of ABC Company has taken the role of Project Sponsor. In other words the project has been directly undertaken by Portfolio. Which of the following statement is appropriate with reference to Portfolio Management?
Refer Scenario 1 – The Project lifecycle was divided into 4 stages. Which of the following statement is TRUE regarding the characteristics of this project life cycle?
Refer Scenario 1 – The project lifecycle is divided into 4 stages. What key action must be taken by the project manager during subsequent phases in order to validate decisions made at the start of project?
Refer Scenario 1 – Which of the following statement appropriately explains the term ‘Risk Tolerance’?
Refer Scenario 1 – “Contract a restructuring specialist to take an assurance role in the project, and provide advice to the Project Sponsor and Project Manager.” This statement is an example of which risk response strategy?
Refer Scenario 1 – “Include a clause in the contract with the selected external supplier stating that, if the full functionality of the software solution is not delivered, the selected external supplier will reduce their fees accordingly.” This statement is an example of which risk response strategy?
Refer Scenario 1 – Which of the following statement appropriately explains the term ‘Proximity’?
Refer Scenario 2 – Based on the data given in the scenario, which activity has the highest float?
Refer Scenario 2 – Based on the data given in the scenario, which activity would be the primary candidate for crashing?
Refer Scenario 2 – The scenario states that you have to use Precedence Diagramming Method (PDM) to draw the network diagram. Which of the following statements is TRUE about Precedence Diagramming Method?
Refer Scenario 2 – If project manager decides to provide a lag of 3 weeks for the activity ‘Evaluate Proposals’. What will be the impact on Project completion?
Refer Scenario 2 – If project manager decides to provide a lag of 3 weeks for the activity ‘Evaluate Proposals’. What will be the changed Critical Path?
Refer Scenario 3 – All deliverables of the project are considered to be complete ……
Refer Scenario 3 – Based on the data in the scenario, What is the Cost Variance on the status date for four deliverables?
Refer Scenario 3 – Based on the data in the scenario, if it is assumed that same performance will continue throughout the project then what is the Estimate At Completion (EAC)?
Refer Scenario 3 – Based on the data in the scenario, What is the Schedule Performance Index on the status date for four deliverables?
Additional Information – “During planning the project manager conducts a brainstorming session with all team members and relevant stakeholders to identify innovative ways to ensure the project’s success.” Group brainstorming encourages all of the following EXCEPT ……
Additional Information – “ABC Company, awarded the contract to Franklin Consultants. The project manager of Franklin consultants has completed the scope validation process. One of the representatives of ABC Company says that a functionality, related to service desk, is missing.” What should the project manager of Franklin Consultants do now?
Additional Information – “The project manager has obtained the approval, for the scope statement, from the sponsor. The project manager and his senior team members are brainstorming to identify the WBS deliverables.” All of the following are benefits of the WBS EXCEPT?
Additional Information – “During the course of the project, The project manager of Franklin Consultants thinks that he has discovered vital trade secrets of ABC Company’s business.” As a seller’s project manager, he should ……
Additional Information – “Some stakeholders requested additional requirements . This resulted in negative impact on Cost and Schedule. But also helped in reducing stakeholders’ resistance to acceptance of the new systems.” What is the preventive action the project manager must take in order to avoid such a risk in future?
Additional Information – “The Initiation phase is in its conclusion phase . However, one team member of Franklin Consultants informs the Project Manger that the QA representative of ABC is not satisfied about the quality of deliverables.” What the project team of Franklin Consultants has failed to do?
Considering the strategic importance of the project, the CEO of ABC Company has taken the role of Project Sponsor. For the project manager of Franklin Consultants what is the most appropriate strategy for engaging with him?
Additional Information – “One of the Functional Manager resigned while the project was in execution phase.” What action should the project manager consider now?
Refer Scenario 3 – What will be the final payment to Franklin Consultants if the project gets completed in 7,60,000 USD?