Which of the following statements is true about Precedence Diagramming Method?
A new ERP system has to be started after the previous is shut down. This is an example of …
What can be said about activities which have a high number of predecessors and/or successors?
The amount of time that an activity can be delayed without delaying the early start date of its successor is known as ……
All of the following is true about Fast tracking, EXCEPT …
The Early Start of an activity is 17. The duration is 7 days. The Late Finish is 34. What is the Float in this activity?
Activity B can start 5 days after the initiation of Activity B. What type of logical relationship would you assign?
The initiation of the successor activity depends upon the completion of the predecessor activity. What relationship is this?
Activity ‘B’ can start 5 days after activity ‘A’ has completed. This is an example of ……
Jack is a project manager working on the development of an e-learning portal. He has information about how many screens need to be developed and how long will his developers take for each screen. Based on this formula he makes estimation. This is an example of …
In a project schedule, few activities were marked as “milestone” activities. This means that …
Crashing has a risk of compromising ……
A customer has not given the complete project requirement and he says: I shall plan the work in near future in details and the work in far future will be detailed at a later stage. This is known as ……
The duration of the Tasks A, B, C, D, E and F are 2, 2, 2, 3, 6, 3 days respectively. B, D and E are the successors of A. The predecessor of C is B. The Predecessors of F are C, D and E. What is the critical path of the network?
Which of the following statement is NOT correct about Summary Activity?
A run chart is a graph that displays observed data in a time sequence. Often, the data displayed represents some aspect of the output or performance of a process. Such a report can provide ……
The primary purpose of a milestone chart is ……
Midway through the project during analysis you find that schedule needs to be compressed. Which activity can you consider crashing?
The project manager is planning to use a computer based simulation software to analyze the behavior of the system. Which of the following technique, is typically used in simulations?
The project schedule presentation may be in summary form or in detail. It is more often presented graphically in different formats like bar charts, milestone charts or network diagrams. One main difference between bar charts and network diagrams is …
Review of any of the following could trigger a need for resource leveling, except …
Due to shortage of resources, half of the resources from the project have been shifted to another project in the organization. To meet the project schedule deadline, The project manager needs to ……
The project manager has completed the project network diagrams and critical path analysis. He is reviewing the calculations again before starting the schedule network analysis. An activity in the network diagram has an ES=4, LS=14 and EF=12 , LF=22. What is true regarding this activity?
Which of the following would be irrelevant if the critical path needs to be reduced by 35% on a project?
During Earned Value Analysis, the project SPI is calculated as 0.78 and the CPI as 0.89. What is the best explanation for this result?