Instructions:
0 of 64 questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Time has elapsed
You have successfully completed the competency quiz.
A project is being executed under a contract which has an incentive clause for early completion. Which of the following will be most helpful in realizing this opportunity?
An NGO is conceptualizing a project to improve availability of potable water in a remote region. Currently the local population has to suffer water shortages during the summer months. Under what circumstances should the project be accepted?
During a Sprint review meeting, one of the end user observes that a certain feature is implemented correctly, but if it is changed slightly, it would be far more useful to them. What should be done with this kind of feedback?
As a best practice the Business Case needs to be evaluated using 1) Do Something 2) Do Minimum 3) Do Nothing options. Which option should be baselined to arrive at best decision?
A project had an initial investment of $100,000 and a forecast benefit of $20,000 in the first year, $30,000 in the second year and $60,000 in the third year. What is the payback period?
During Earned Value Analysis the project Schedule Performance Index(SPI) is calculated as 0.78 and the CPI as 0.89. What is the best explanation for this result?
An engineering company had a policy of creating annual maintenance contracts for all the critical equipment to prevent down time during critical phases of the project. How should it decide the maximum amount it should pay for these contracts?
Your customer’s IT process is experiencing substantial errors in dispatch and billing of finish goods. Your project provides input to customer’s billing process. Customer has not provisioned for revamping his dispatch and billing process. What should you do to convince the customer to provide budget for seamless performance of the entire system?
An insurance company is initiating a project to develop a system for audits to meet a regulatory mandate that will come into force in the next financial year. Which of the following is the best set of methods to apply in order to secure authorization for the project?
Your project is ahead of schedule but overrunning the cost. What would be an appropriate action in such a scenario?
Having categorized stakeholders according to their power and interest, you wondered about how to engage stakeholders having low power and high interest. Which of the following could be the best approach?
Your customer has directly informed the team member to begin the work on new deliverables of next phase. He is a high value customer from organization’s perspective. As a project manager …
The project manager has completed the project network diagrams and critical path analysis. He is reviewing the calculations again before starting the schedule network analysis. An activity in the network diagram has an Early Start = 4, Late Start = 14 and Early Finish = 12 , Late Finish = 22. What is true regarding this activity?
You have closed a project with a delay of 4 months. What would be the Schedule Performance Index (SPI) after the project is closed?
Your project is in Execution phase. Your project sponsor (from customer organization) is from Manufacturing department. Due to restructuring initiative in customer organization, your new sponsor will be from IT department. What should you do?
You are in the midst of planning a project with your team. There is a conflict between the team members about whether duration and number of phases should be more or less. Which one of the following is true regarding planning of number of phases?
A team member is assigned to a project by a Resource Manager. It is observed that the resource has the necessary skills and knowledge but not performing upto the standard. What can be done in this situation?
Which of the following BEST explains how can you improve the value delivered to the customer?
A Scrum team has failed to meet its Sprint commitments. The primary cause was a wrong design decision taken by two of the members assigned to a core story. As a Scrum Master, what should be your approach during the Sprint retrospective?
A project is behind schedule and under budget. Which of the following scenarios might cause this to happen?
Due to financial constraints your management has requested that you reduce the budget for the project by 5%.What will this probably mean for your project?
An organization is working on Project A for 2 years. With the change in technology recently a new project B is being evaluated to deliver a similar solution. A sum of $500,000 has been invested in Project A already and another $390,000 are needed to complete it. Project B needs $450,000. Only one project can be chosen. How should the decision be made?
A project manager is wondering what is the best way to report on the project status. Some of the options being considered are: Emailed documents, Web based dashboard with link circulated to all, Formal meeting to share information, etc. How should the decision be made?
Midway through the project during analysis you find that schedule needs to be compressed. Which activity can you consider crashing?
During product development, one of the team members suggested an idea that would improve ease of use of the application. The cost of development would be negligible. What should be the next step?
Stories A and B both deliver similar value but A is a bit more risky to implement than B. Stories C and D have lower value than A and B but C is low risk whereas D is high risk. Which story should be implemented first in a time-boxed release?
Some mandatory tests (like crash tests) on an automobile are destructive tests. What approach should be used for carrying out such tests?
A product created by the project is ready for deployment. During the transition process, the Manager of the operations team suggested some extra expenditure that would greatly improve the service experience and drive future sales. What should be the approach?
A project is highly research oriented and there is no clarity about the goal or the proposed solution. What is the best approach for the project manager?
Your project operates within cross-organizational reporting framework. Since resources are from different verticals and have no direct reporting relationship with you. What would be the biggest challenge for you in this situation?
A project has well defined scope with a minimum risk of major changes from the customer. Which type of contract is most preferred in this scenario?
The team member knows that one milestone has been delayed, but the monthly report to the customer shows zero schedule variance. Which one of the following is not being reported correctly?
According to you which of the following would help your organization to get repeat business after closing the project?
During the final stages of IT product development, one of the Steering Committee members suggested that the test and pre-launch marketing should also be managed under the Program. The marketing project is outsourced under different budget. As a Program Manager how should you respond?
The most beneficial role for the Program Manager in Change Management activities at Program level is:
All the components of the Program have been closed, the lessons learned were documented and formal sign-offs on the deliverables were received. Which of the following is the most important additional step that needs to be performed for the Program to be formally closed?
Project A is part of a Program. During risk identification and response planning, the Project Manager had identified a risk, for which the response plan was identified as “Accept”. The risk event has actually occurred, causing a cost increase of 300,000 USD. How should this be handled within the Program?
The most important reason of higher level of uncertainty within a Program as compared to project is…..
The CIO of a large finance organization recommended CMMi practices for their IT support. The board has approved this recommendation but remains skeptical about the business value of this exercise. Which of the following would BEST help you as a Program Manager and the CIO (who is also the Program Sponsor) keep the Board members engaged in the Program?
One of the projects in your Program may undergo a drastic change in scope and cost due to change in regulations. In order to make a Go/ No Go decision for this project you would…
You are appointed as a Program Manager to oversee an ambitious product development initiative in an organization. The products envisaged and the technology as well as domain is new to the organization. In the initiation of the Program, what should be the most important concern for you?
Which of the following is a good practice regarding resource management for a Program and its components?
At a Program review, many Project Managers pointed out that it is very difficult to coordinate work because of strong functional loyalties which cause friction between the teams. For instance, the engineering and the testing teams are constantly at loggerheads because of conflicting goals. What would you do as Program Manager?
When a process is operating at three sigma, what is the level of accuracy that is implied?
There is a high degree of risk in your project about the customer’s approach. His influence is likely to be very high throughout the project. In order to manage this risk, you will …
Your customer is always keen on driving his point of view during project meetings. The project needs a change and there is a disagreement about the solution between you and the customer. You would resolve this conflict in favor of…
You are assigned for a project due to resignation of the existing project manager. The project is 25% complete. In order to continue with this project you will…
During project execution it is advisable that…
Administrative closure of project is complete and it is handed over to operations. The customer has suggested some minor changes to improve the efficiency in operations. This will be treated as…
During project execution, you see an opportunity of saving 80,000 USD by using different technology which is not mentioned in project scope. This is…
Which of the following is a true statement regarding Project Stakes (Project stakes could be tangible or intangible)?
A team is trying to define the scope of Value Stream Analysis (A value stream is the set of actions that take palce to add value to a customer from initial request through realization of value). The most appropriate approach would be to consider it…
Review of any of the following could trigger a need for resource leveling, EXCEPT…
Project scope means …
Confirming the readiness of operational environment, post-delivery, is responsibility of…
A project team is tasked to develop an innovative design using multiple technology platforms. The team is in brainstorming session to come up with a candidate list of features. Which of the following would NOT be a good idea during this meeting?
During penultimate review of the project, your team leader reports that the project is well ahead of schedule and there is some costs saving. This is…
You are in the midst of planning the project. You have tasked one of the team members to provide duration and dependencies of activities related to his deliverables. The team member has promptly submitted the bar chart with all details. This is…
As a project manager, you manage multiple projects. One of your projects is over budget while the other is under budget. You decide to transfer money from the latter to the former and report both projects as within budget. This is called…
During project review meetings you observed that your stakeholders tend to deviate the discussions from agreed agenda. In order to keep focus on the meeting agenda, you would…
Your project site is located in a politically sensitive area where local population is a negative stakeholder to the project. In order to handle this risk you will…
During execution of the project, your customer points a mistake in execution which will lead to rework. The cost baseline is agreed between your company and customer’s company. In order to execute the rework you would …
During execution you realize that a minor modification in scope in your project will save good amount of money for your company. This modification is not affecting the customer’s expectation. As a project manager you would…
Influencing ability of the stakeholders on a project is…